What leaves the plan when the CEO adds a request?

The CEO needs an investor presentation by Thursday. Your week is already allocated.

The question

Kestrel Workflows is a fictional US-based B2B software company. Use only this case packet.

Agreed work and new request
Hours
Board preparation8
Cross-team renewal fix12
AI vendor pilot10
New presentation6

The first three items fill the agreed plan. You have 30 delivery hours after fixed duties. The board and renewal deadlines are fixed.

New request and decision rights

The presentation needs 6 hours. The whole 10-hour pilot can move one week without a customer or contract impact. It needs an uninterrupted commitment. The CEO agrees changes to the priority plan.

“Choose your next move and explain the decision it supports.”

A strong answer, step by step

Open each step in turn. This is one strong answer, not the only one.

Step 1: Choose the first response

What would you do here? Open the move you’d make.

  • Promise to do everything

    Tempting, but it misses something. The 36-hour plan exceeds the 30-hour capacity.

  • Take a trade-off to the CEO

    The strong move. A new request changes an already full plan.

See how a strong candidate says it

“I will show the CEO what the new request displaces before accepting it.”

What a strong candidate could say

Why it works: A new request changes an already full plan.

Step 2: Make a feasible recommendation

What would you do here? Open the move you’d make.

  • Defer the 10-hour pilot

    The strong move. The pilot can move; the two fixed commitments cannot.

  • Drop the board preparation

    Tempting, but it misses something. That breaks a fixed commitment without agreement.

See how a strong candidate says it

“Defer the pilot. Board work, the renewal fix and the presentation use 26 hours, leaving 4 hours of buffer.”

What a strong candidate could say

Why it works: The pilot can move; the two fixed commitments cannot.

Step 3: Update: the CEO now needs only a 2-hour outline this week

What would you do here? Open the move you’d make.

  • Restore the full pilot immediately

    Tempting, but it misses something. The shorter outline still leaves the week 2 hours over capacity.

  • Recheck capacity before restoring the pilot

    The strong move. The smaller request still does not fit beside every original commitment.

See how a strong candidate says it

“Keep the whole pilot deferred. The revised plan uses 22 hours; restoring all 10 pilot hours would make it 32.”

What a strong candidate could say

Why it works: The smaller request still does not fit beside every original commitment.

Step 4: Close the agreement

What would you do here? Open the move you’d make.

  • Record the agreed plan and review point

    The strong move. An explicit agreement makes the change visible to those waiting for the work.

  • Quietly delay the pilot

    Tempting, but it misses something. The waiting team cannot plan around an undisclosed change.

See how a strong candidate says it

“Confirm the board work, renewal fix and outline this week. Move the pilot one week and review the plan with the CEO.”

What a strong candidate could say

Why it works: An explicit agreement makes the change visible to those waiting for the work.

The answer, in short

Decision
Agree the revised plan with the CEO and defer the full pilot.
Because
The outline reduces the new work, but does not make every original commitment fit.
What would change it
A smaller agreed pilot scope or a released fixed commitment would change the options.

Common traps

  • A polished update does not replace an agreed decision and owner.

Check your answer

  • I checked capacity.
  • I protected the fixed commitments.
  • I showed what moves.
  • I named who agrees the change.